An Earth Day treat: lots of renewable energy for our Iowa data center
4/22/14
We’ve been talking to MidAmerican Energy, our energy supplier in Iowa, about renewable energy since we started building our
Iowa data center
in 2007. Just in time for Earth Day, we now have a freshly inked agreement with MidAmerican Energy to supply our Iowa data center facilities with up to 407 MW of 100% renewable wind energy, as tracked by renewable energy certificates. This agreement will not only cover our current facilities but will allow for future expansion supplied by renewable energy as well.
This is our
seventh and largest renewable energy commitment
to date, bringing the total amount of renewable energy we’ve contracted for to over one gigawatt (1,000 megawatts).
We’ve entered into a few different kinds of agreements over the years - sometimes signing power purchase agreements (PPAs) with wind farm developers and sometimes working with our local utility partners. This agreement is similar to our
2012 agreement
with our Oklahoma utility, the Grand River Dam Authority. In this case, MidAmerican Energy will sell energy to our Iowa data center bundled with and tracked by renewable energy certificates generated by projects that are part of its
Wind VIII program
.
PPAs and agreements like this one are a big part of the
commitment to carbon neutrality
we made back in 2007, and we’re working to make this whole process easier for other companies by advocating for
renewable energy tariffs
. Depending on the circumstances, any of these approaches can make sense, and we’re always on the hunt for new and creative ways to
power our operations
with renewable energy. But it’s not just our own operations we want to green: Google has also invested over $1B in 15
renewable energy investments
around the world in an effort to put more renewable energy on the grid and reduce global greenhouse gas emissions.
We’ll continue working with MidAmerican Energy and all of our utility partners to find diverse ways to deliver clean, renewable energy to our data centers. Happy Earth Day!
Posted by Neha Palmer and Sam Arons, Wind Ninjas
More Swedish wind power for our Finnish data centre
1/22/14
(Cross-posted from the
Google Europe Blog
)
We’re keen to make sure that our data centres around the world use as much renewable energy as possible. By entering into
long-term agreements
with wind farm developers over the past few years, we’ve been able to increase the amount of renewable energy we consume while helping enable the construction of new facilities.
Today we announced that we’ve signed a new power purchase agreement (PPA) in Sweden (our
second such agreement
there in less than 12 months). We will buy the entire electricity output of four as-yet-unbuilt wind farms in southern Sweden, at a fixed price, for the next ten years.
Windfarm developer
Eolus Vind
will build four wind farms, in Alered, Mungseröd, Skalleberg and Ramsnäs, Sweden. The 29-turbine project, with a total combined capacity of 59MW, already has all relevant planning approvals and permits and will become fully operational in early 2015.
Our seawater-cooled data centre in Hamina, Finland
Once completed, the wind farms will provide Google’s Hamina, Finland, data centre with additional renewable energy as the facility
expands
in coming years.
Buying renewable energy in Sweden and consuming it in Finland is possible thanks to Europe’s increasingly integrated power markets, in particular the Nord Pool spot market. This allows Google to buy renewable energy with Guarantee of Origin certification in Sweden, “retire” the certificates and then consume an equivalent amount of power elsewhere in Europe.
This marks our sixth long-term agreement to purchase renewable energy. We keep signing these contracts for two main reasons: they make great financial sense for us, and increase the amount of renewable energy available in the grid, which is great for the environment too.
Posted by Francois Sterin, Director, Global Infrastructure Team
A new wind investment in Texas
1/14/14
(Cross-posted from the
Official Google Blog
)
It sure is windy in Texas. So windy, in fact, that we’ve made
another
wind energy investment there. In late December we finalized an agreement to invest $75 million in the Panhandle 2 wind farm in Carson County, outside of Amarillo. The 182MW facility, developed by leading wind developer Pattern Energy Group LP, has the capacity to generate enough renewable energy to power 56,000 U.S. homes. We expect the facility to be operational by the end of 2014.
The future sight of Pattern's Panhandle 2 wind farm
Panhandle 2 is our
15th renewable energy investment overall
, and our second in Texas—last year around this time we announced an approximately $200 million investment in the
Spinning Spur wind farm
. In addition to these two projects, we’re also buying Texas wind from the
Happy Hereford wind farm
as part of our
goal
of operating on 100 percent renewable energy. These efforts reflect our long-standing commitment to renewable energy as both an investor and a consumer.
Sunset at another Pattern facility, Gulf Wind
Let that Texas wind blow!
Posted by Nick Coons, Principal, Renewable Energy
An update on our efforts to expand options for companies to buy renewable energy
11/15/13
Back in April, as part of an
announcement
that we were expanding our Lenoir, N.C. data center, our electricity provider Duke Energy committed to developing a new program to enable companies to buy renewable energy directly from the utility. At the time we also published a
white paper
explaining why we think this is important.
Since then, we and others have been providing input on the development of a pilot program, which will officially be called the Green Source Rider. We’re pleased to report that Duke
just filed
their
proposal
for the Rider with the North Carolina Public Utilities Commission (NCUC) for approval. While the Rider still needs to be vetted by stakeholders and approved by the NCUC, we applaud Duke for developing a new option for customers to green their power supplies in North Carolina.
Our long-term goal is to power our data centers with 100% renewable energy, and we look forward to working with Duke and others to find cost-effective renewable energy options that can be offered under the Green Source Rider. It’s our hope that this effort will encourage additional development of clean energy in North Carolina and elsewhere for growing companies like Google.
Posted by Gary Demasi, Director, Global Infrastructure
Solar in California and Arizona: More of a good thing
11/14/13
(Cross-posted from the
Official Google Blog
)
You’d think the thrill might wear off this whole
renewable energy investing thing
after a while. Nope—we’re still as into it as ever, which is why we’re so pleased to announce our 14th investment: We’re partnering with global investment firm KKR to invest in six utility-scale solar facilities in California and Arizona. Developed by leading solar developer Recurrent Energy, the projects have a combined capacity of 106MW and will generate enough electricity to power over 17,000 U.S. homes. Google will make an approximately $80 million investment into these facilities.
The 17.5 MWac/22 MWp Victor Phelan project (pictured), located in San Bernardino, Calif., is part of six Recurrent Energy developed projects acquired by Google and KKR. The six-project portfolio is expected to operational by early 2014 and will generate enough clean electricity to power more than 17,000 U.S. homes.
This investment is similar to one we made
back in 2011
, when we teamed up with KKR and invested $94 million in four solar facilities developed by Recurrent. Those facilities have since started generating electricity, and we’ve committed hundreds of millions more—more than $1 billion in total—to renewable energy projects around the world.
These investments are all part of our drive toward a clean energy future—where renewable energy is abundant, accessible and affordable. By
continuing to invest
in renewable energy projects,
purchasing clean energy
for our operations and
working with our utility partners
to create new options for ourselves and for other companies interest in buying renewable energy, we’re working hard to make that future a reality.
Posted by Kojo Ako-Asare, Head of Corporate Finance
A solar investment in California’s Imperial Valley
10/10/13
We’re celebrating Halloween early with our “lucky thirteenth” renewable energy investment: a $103 million commitment to Mount Signal Solar, a 265.7 MW solar photovoltaic plant in Imperial County, CA. The project will generate enough energy to power 80,000 homes.
Like many states, California has a
goal
of increasing the amount of energy procured from renewable sources. The energy from Mount Signal Solar, which has been contracted to San Diego Gas & Electric, will help California meet this goal. The project, which is owned and operated by Silver Ridge Power (formerly AES Solar), will also create over 900 construction jobs in a part of the state that suffers from high unemployment.
Thirteen renewable energy investments in three years!
That’s a lot of energy—the over $1 billion we’ve committed to these projects will generate enough electricity each year to power more than 500,000 U.S. homes. Why are we making these investments? It’s simple: we believe in a clean energy future, and we think that companies like ours can help make it happen. We invest in these projects because they make business sense, because they help put more renewable energy on the grid, and because they have a positive impact on the local economies where they operate.
The Mount Signal Solar project in Imperial County, CA
Posted by Kojo Ako-Asare, Head of Corporate Finance
Another windy day in Texas: a new power purchase agreement
9/17/13
(Cross-posted on the
Official Google Blog
)
As part of our quest to power our operations with 100% renewable energy, we’ve agreed to purchase the entire output of the 240 MW Happy Hereford wind farm outside of Amarillo, Texas. This agreement represents our fifth long-term agreement and our largest commitment yet; we’ve now contracted for more than 570 MW of wind energy, which is enough energy to power approximately 170,000 U.S. households.
The Happy Hereford wind farm, which is expected to start producing energy in late 2014, is being developed by
Chermac Energy
, a small, Native American-owned company based in Oklahoma. The wind farm will provide energy to the Southwest Power Pool (SPP), the regional grid that serves our Mayes County, Okla. data center.
Some (happy) cows on the future site of the wind farm.
The cows will still have plenty of room to graze between the turbines.
The structure of this agreement is similar to our earlier commitments in
Iowa
and
Oklahoma
. Due to the current structure of the market, we can’t consume the renewable energy produced by the wind farm directly, but the impact on our overall carbon footprint and the amount of renewable energy on the grid is the same as if we could consume it. After purchasing the renewable energy, we’ll retire the renewable energy credits (RECs) and sell the energy itself to the wholesale market. We’ll apply any additional RECs produced under this agreement to reduce our carbon footprint elsewhere.
This type of power purchase agreement represents one of
several ways
we’re working to make additional renewable energy available for both our data centers and the communities in which we operate. In Scandinavia, due to the region’s unified power market and grid system, we’re able to
purchase wind energy in Sweden
and directly consume it at our Hamina, Finland data center. We’re also working with our local utility partners to develop new options. In 2012, we signed an agreement with GRDA, our utility partner in Oklahoma, to
green the energy supply
to our Oklahoma data center with 48 MW of wind energy from the Canadian Hills Wind Project. Earlier this year, we began
working with Duke Energy
to develop a new
renewable energy tariff
(PDF) in North Carolina.
We take a comprehensive approach to acquiring renewable energy for our operations. We’ll continue working directly with utility providers, collaborating with industry regulators and pursuing
creative agreements
(PDF) like the Happy Hereford PPA.
Posted by Matt Pfile, Senior Manager, Data Center Energy and Location Strategy
Archive
2016
Sep
Aug
Jul
Jun
Apr
Feb
2015
Dec
Nov
Oct
Sep
Aug
Jul
Feb
2014
Dec
Nov
Sep
Aug
Jul
Jun
May
Apr
Jan
2013
Nov
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
Jan
2012
Dec
Nov
Oct
Sep
Jul
Jun
May
Apr
Mar
Jan
2011
Dec
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
Feb
Jan
2010
Dec
Nov
Oct
Aug
Jul
May
Apr
Mar
Feb
Jan
2009
Dec
Nov
Oct
Aug
Jul
Jun
May
Apr
Mar
Feb
Jan
2008
Dec
Nov
Oct
Sep
Aug
Jul
Jun
May
Apr
Mar
Jan
2007
Dec
Nov
Oct
Sep
Aug
Jun
2006
Nov
Oct
Feed
Google
on
Follow @google
Follow
More Google Green
Google Green site
Google Data Centers site